An engineering reference for specifying engineers, OEM cable approvers, and procurement teams working with reeling drum cables under the German VDE 0250 Part 813 standard. This document presents the standards framework defining VDE 0250 Part 813 reeling cables, the construction architecture this standard mandates, the type test battery that qualifies a cable to the standard, and the engineering basis on which Anhui Feichun Special Cable Co., Ltd. (安徽飞纯特种电缆有限公司) supplies VDE 0250 Part 813-compliant reeling cable as a direct equivalent to the Nexans (N)TSCGEWTOEUS family.

▣ VDE 0250-813 COMPLIANT ▣ IEC 60502-1/-2 ALIGNED ▣ DRUM-OPTIMIZED CONSTRUCTION ▣ TYPE-TESTED FOR REELING SERVICE
Trademark and Reference Notice Nexans® and (N)TSCGEWTOEUS are designations used by Nexans S.A.; references herein are for technical cross-reference only. Anhui Feichun Special Cable Co., Ltd. is an independent specialty cable manufacturer not affiliated with, sponsored by, or endorsed by Nexans S.A. The equivalent product described in this document is engineered against the public VDE 0250 Part 813 standard and is qualified independently against the standard’s published acceptance criteria.
VDE
VDE 0250-813
Reeling cables for cranes, hoists, and mining equipment subject to repeated drum reeling cycles
IEC
IEC 60502-1/-2
Power cables 1 kV through 30 kV — extruded insulation, screen design, and electrical performance
DIN
DIN VDE 0282
Polymer-insulated cable construction requirements, insulation and sheath compounds, mechanical properties
HD
HD 22.4 / IEC 60228
Conductor classification and stranding requirements; flexible Class 5 and Class 6 fine-wire conductor specifications
§ 01
Standard Scope and Engineering Intent

What VDE 0250 Part 813 Defines

VDE 0250 Part 813 is the German cable standard defining construction, performance, and testing requirements for reeling cables — that is, flexible cables specifically designed for repeated winding and unwinding on motorized cable drums (reeling drums) installed on cranes, mining shovels, draglines, container handling equipment, port equipment, and similar mobile or relocatable machinery. The standard is one of several parts within the larger VDE 0250 family covering rubber-insulated and polymer-insulated cables for power installations; Part 813 specifically addresses the unique mechanical demands of drum reeling service, which differ materially from the demands placed on stationary power cables, conventional trailing cables, or general-purpose flexible cables.

Reeling drum service imposes a specific failure mode on cables: each reeling cycle subjects every section of cable to a defined sequence of mechanical events — straightening as the cable pays out, controlled bending as it spirals onto the drum, layer-on-layer compression as successive turns load atop earlier turns, and repeated friction at layer transitions. A surface-mining shovel reel cable executing 4,000 reeling cycles per year, over a 5-year service expectation, sees 20,000 full mechanical fatigue cycles. A port container crane reel cable can exceed this by an order of magnitude. Cables not engineered specifically for this duty fail through conductor strand breakage at flex points, sheath fatigue cracking at bending zones, insulation displacement under compression, or layer-to-layer abrasion damage. VDE 0250 Part 813 exists to define the cable engineering response to this specific service environment.

SCOPE DEFINITION

VDE 0250 Part 813 applies to: flexible cables with rubber insulation (predominantly EPR / EPDM) and rubber outer sheath (CPE, CR/Neoprene), Class 5 or Class 6 fine-wire stranded copper conductors, voltage classes from 0.6/1 kV through 6/10 kV, intended for service on motorized cable drums where the cable experiences repeated reeling and unreeling cycles under defined tensile, bending, and compressive loading conditions. The standard establishes minimum conductor stranding fineness, insulation and sheath compound performance criteria, dimensional construction requirements, and the type test battery — including the characteristic reeling fatigue test — by which a cable is qualified as suitable for reeling drum service.

Distinguishing Reeling Cables from Trailing Cables

A frequent source of specification confusion in mining and crane procurement is the distinction between trailing cables and reeling cables. Both terms are sometimes used interchangeably in vendor literature, but the engineering basis is different. Trailing cables are dragged behind moving equipment along the ground; their primary mechanical demands are abrasion, impact from rocks and obstacles, longitudinal tension under drag loading, and exposure to ground hazards including spillage of hydraulic oil, diesel fuel, and process water. Standards such as VDE 0250 Part 812 (trailing cables) and Type SHD-GC under ICEA S-75-381 in the Americas address this duty.

Reeling cables, in contrast, are wound onto and unwound from a powered drum; their primary mechanical demands are repeated bending fatigue, layer-on-layer compression, and friction during reeling transitions. While the cable may incidentally experience drag, abrasion, and impact, these are secondary considerations to the reeling duty itself. VDE 0250 Part 813 governs this duty. The Nexans (N)TSCGEWTOEUS family is engineered specifically as a reeling cable — the construction features (Class 6 conductor stranding for maximum flexibility, optimized insulation and sheath geometry for bending, textile reinforcement to resist tear propagation under bending stress) are reeling-cable-specific engineering choices. Specifying a trailing cable for a reeling application, or a reeling cable for a trailing application, can produce passable initial performance and premature failure as the wrong failure mode dominates.

▣ Engineering Note: Application-Driven Specification

The (N)TSCGEWTOEUS designation includes the “T” (trailing) character within German cable nomenclature, which reflects the fact that VDE classification historically treated reeling and trailing cables within overlapping designation systems. Modern VDE 0250 Part 813 explicitly addresses reeling duty as the controlling design criterion. Many real-world applications — particularly surface mining shovels with cable reels and port crane reeling drums — combine elements of both duties. The (N)TSCGEWTOEUS construction is engineered to perform under both duties, with reeling fatigue resistance as the dominant design driver and trailing-cable mechanical robustness as the supporting envelope.

§ 02
Construction Requirements per VDE 0250 Part 813

The Construction Architecture VDE 0250 Part 813 Requires

VDE 0250 Part 813 prescribes specific construction requirements that distinguish a qualified reeling cable from a generic flexible power cable. These requirements operate at every layer of the cable construction: conductor, conductor screen (medium-voltage), insulation, insulation screen, concentric earth conductor, reinforcement layer, and outer sheath. Compliance at every layer is required for full standard qualification; partial compliance produces a cable that is suitable for some service but fails the VDE 0250-813 acceptance test at the omitted requirement.

2.1. Conductor Construction (VDE 0250-813 § Conductor Requirements)

Construction ElementVDE 0250-813 RequirementEngineering BasisFeichun Compliance
Conductor metalAnnealed copper, ETP gradeMaximum conductivity and ductility for repeated flexingCompliant
TinningHot-dip or electrolytic tin coatingPrevents copper-rubber sulfide reaction in EPR insulationCompliant — hot-dip standard
Stranding class (≤ 25 mm²)Class 5 minimum per IEC 60228Minimum strand fineness for required flexibilityClass 5 standard
Stranding class (≥ 35 mm²)Class 5 or Class 6 per IEC 60228Class 6 preferred for higher reeling cycle countsClass 6 standard ≥ 95 mm²
Strand diameter (typical)0.21–0.51 mm depending on sizeSmaller strands = higher flexibility, lower fatiguePer IEC 60228 table
Bunched-then-stranded constructionRequired for Class 5/6Bunched bundles of strands then twisted into rope constructionCompliant
Conductor lay length≤ 12 × bunch diameter (typical)Tighter lay improves flexibility, increases material usageCompliant
DC resistance @ 20°CPer IEC 60228 max. resistance tableDefines minimum copper cross-sectionRoutine tested 100%

2.2. Insulation System (VDE 0250-813 § Insulation Requirements)

Construction ElementVDE 0250-813 RequirementEngineering BasisFeichun Compliance
Insulation materialEPR / EPDM, peroxide-curedThermosetting, maintains properties at elevated temperaturePeroxide-cured EPR
Insulation thickness, 0.6/1 kV1.4 mm nominal min.Per VDE 0282 voltage class table1.4 mm standard
Insulation thickness, 1.8/3 kV2.4 mm nominal min.Per VDE 0282 voltage class table2.4 mm standard
Insulation thickness, 3.6/6 kV3.4 mm nominal min.Per VDE 0282 voltage class table3.4 mm standard
Insulation thickness, 6/10 kV4.5 mm nominal min.Per VDE 0282 voltage class table4.5 mm available
Conductor screen (≥ 1.8/3 kV)Extruded semiconductive EPRSmooths field at conductor surfaceTriple-extruded with insulation
Insulation screen (≥ 1.8/3 kV)Extruded semiconductive EPR, strippableDefines outer field boundaryTriple-extruded, strippable
Insulation tensile (initial)≥ 4.2 N/mm²VDE 0282 acceptance criterion≥ 4.5 N/mm² typical
Insulation elongation (initial)≥ 200%Ductility for bending without cracking≥ 220% typical
Insulation tensile (after aging)≥ 70% of initial valueLong-term thermal stability requirement≥ 80% typical
Hot-set test≤ 175% elongation under load at 200°CConfirms peroxide cure crosslinkingCompliant

2.3. Earth Conductor and Reinforcement (VDE 0250-813 § Earthing and Reinforcement)

Construction ElementVDE 0250-813 RequirementEngineering BasisFeichun Compliance
Earth conductor typeConcentric tinned copper braidSurrounds power cores, maximizes earth fault detectionConcentric tinned Cu braid
Earth conductor cross-section≥ 50% of phase conductor; 100% for high-fault systemsCarries fault current safely until protection operates50% / 100% per option
Earth conductor coverage≥ 80% optical braid coverageContinuous earth path along cable length≥ 85% typical
Pilot conductor (optional)For monitored ground systemsCarries ground continuity monitoring signal2.5 mm² standard
Reinforcement layerTextile braid (polyester or aramid)Tear propagation resistance, longitudinal strengthAramid braid standard
Reinforcement coverageContinuous longitudinal coverageNo gaps in tear-stop layerContinuous helical braid

2.4. Outer Sheath (VDE 0250-813 § Sheath Requirements)

Sheath PropertyVDE 0250-813 RequirementTest MethodFeichun Performance
Sheath materialCPE / CR (Neoprene), peroxide-curedMaterial identification, FTIR analysisPeroxide-cured CPE/CR
Sheath tensile strength≥ 10.0 N/mm² initialVDE 0282 / DIN 53504 dumbbell≥ 11.0 N/mm² typical
Sheath elongation at break≥ 300% initialVDE 0282 / DIN 53504 dumbbell≥ 320% typical
Sheath tear strength≥ 12 N/mmISO 34-1 / ASTM D624 trouser tear≥ 13 N/mm typical
Tensile after aging (135°C, 168 h)≥ 70% of initial valueVDE 0282 oven aging≥ 80% typical
Elongation after aging≥ 70% of initial valueVDE 0282 oven aging≥ 80% typical
Oil resistance (IRM 902, 70°C, 168 h)Volume change ≤ +20%; mechanical retention ≥ 60%VDE 0473 oil immersion≤ +18%, ≥ 70% retention
Cold flexibility (-40°C)No cracking after mandrel bendVDE 0282 cold bend testCompliant
Abrasion resistanceProject-specified (Taber CS-17, 1 kg)ISO 5470 / ASTM D4060≤ 180 mg / 1,000 cycles
UV / weather resistancePass artificial weathering exposureISO 4892 / DIN EN 50289Compliant
§ 03
The Reeling Fatigue Test — Defining Acceptance Criterion

The VDE 0250 Part 813 Reeling Fatigue Test

The reeling fatigue test is the centerpiece of VDE 0250 Part 813 qualification and the test that distinguishes a true reeling cable from a flexible cable that happens to be marketed for reeling service. The test subjects a representative cable sample to a defined number of reeling and unreeling cycles on a test drum sized to match the cable’s specified minimum dynamic bend radius, under controlled tension and ambient conditions, with electrical performance verification at the end of the cycle count.

Reeling Cycle Count
≥ 50,000
cycles minimum, full reel + unreel sequence
Test Drum Diameter
≥ 10×
cable outer diameter (dynamic bend radius)
Tension During Reeling
Defined
per cable size, simulating service conditions
Post-Test HV Withstand
4× U₀
5 minutes; pass = no breakdown, no flashover

3.1. Reeling Test Methodology

The reeling fatigue test replicates, in compressed laboratory time, the mechanical history a cable experiences over years of service on an actual reeling drum. The test cable sample (typically 30–50 metres of cable) is mounted on a test drum of specified diameter and reeled and unreeled at a controlled speed, with a tensioning system maintaining a defined back-tension on the cable as it spools. The cycle continues for the prescribed cycle count — 50,000 cycles is the standard minimum for VDE 0250-813, with higher counts (100,000+ cycles) specified for premium classes and high-cycle applications such as port container cranes and steel mill ladle cars. Throughout the cycle, the cable is subject to:

  • Repeated bending fatigue at the drum entry/exit point, where the cable transitions from straight to wrapped configuration once per reeling event;
  • Layer-on-layer compression as successive turns wrap atop earlier turns, with the bottom layers experiencing peak compressive load equal to the cumulative weight of all overlying turns plus tension forces;
  • Friction and chafing between adjacent turns and between cable and drum flange surfaces during reeling transitions;
  • Tension cycling as the cable alternates between high-tension wound state and low-tension unwound state.

At the end of the cycle count, the test cable is inspected for visible damage (sheath cracking, insulation displacement, conductor exposure), then subjected to AC voltage withstand testing at four times rated voltage (4 × U₀) for five minutes. Pass criteria require no electrical breakdown, no flashover, no insulation puncture, and no observable mechanical damage that would compromise continued service. Cables that pass the reeling fatigue test at the prescribed cycle count are qualified for VDE 0250-813 reeling service; cables that fail are not.

3.2. Reeling Test Result Interpretation

Cycle Count AchievedService Life ImplicationApplication SuitabilityStandard Class
< 25,000 cyclesInadequate for reeling serviceNon-reeling applications onlyFails VDE 0250-813
25,000 – 50,000 cyclesMarginal for reeling serviceLight-duty reeling, low cycle frequencyBelow VDE 0250-813 minimum
50,000 – 100,000 cyclesStandard reeling service qualificationMining shovels, dragline, general industrial reelingVDE 0250-813 standard class
100,000 – 200,000 cyclesHigh-cycle reeling servicePort cranes, container handling, intensive cyclingVDE 0250-813 enhanced class
> 200,000 cyclesPremium reeling serviceShip-to-shore cranes, RMG/RTG cranes, automated terminalsPremium / project-qualified
▣ Feichun TSCGEWTOEUS-EQ Reeling Performance

Anhui Feichun’s TSCGEWTOEUS-EQ series is qualified to the VDE 0250-813 standard class as the production baseline (≥ 50,000 cycles), with enhanced class qualification (≥ 100,000 cycles) available as a specified option for port crane and high-cycle applications. Type test reports documenting reeling cycle count, post-test electrical withstand performance, and post-test mechanical inspection results are available to qualified buyers under appropriate confidentiality. Where applications require qualification beyond standard class — for example, automated container terminal applications targeting 250,000+ cycles — Feichun supports the extended type testing through the witnessed qualification program.

§ 04
Electrical Performance Specification

Electrical Performance Under VDE 0250 Part 813

Electrical performance requirements for VDE 0250-813 cables align with the broader IEC 60502-1 (low voltage) and IEC 60502-2 (medium voltage) framework, with specific reeling-cable considerations applied through reduced ampacity factors (recognizing the heat dissipation impact of cables wound on drums) and tighter partial discharge limits (recognizing that mechanical bending stress can initiate partial discharge at construction discontinuities).

4.1. Voltage Class and Withstand Performance

Voltage Class U₀/U (U_m)AC Withstand (5 min)Impulse Withstand (1.2/50 µs)Insulation Resistance (20°C)
0.6/1 kV (1.2)3.5 kV—≥ 10⁴ MΩ·km
1.8/3 kV (3.6)10.5 kV40 kV≥ 10⁴ MΩ·km
3.6/6 kV (7.2)21 kV60 kV≥ 10⁴ MΩ·km
6/10 kV (12)35 kV95 kV≥ 10⁴ MΩ·km

4.2. Partial Discharge Performance

Partial discharge measurement is a particularly sensitive indicator of cable construction quality in reeling service, because the repeated bending the cable experiences in service can amplify the electrical stress at any minor construction discontinuity. A cable that meets partial discharge limits at manufacture but has marginal screen-insulation interface quality will see partial discharge inception migrate to lower voltage levels as the cable ages under reeling stress, eventually reaching service voltage and producing accelerated insulation aging at the discharge site. VDE 0250-813 cables therefore require not only acceptance partial discharge measurements but extinction voltage performance demonstrating that any partial discharge initiated at elevated voltage extinguishes at voltages safely above operating voltage.

PD Acceptance CriterionTest VoltageVDE LimitFeichun Result
PD inception voltageIncreasing voltage to detect first PD≥ 1.5 × U₀≥ 2.0 × U₀ typical
PD extinction voltageDecreasing voltage to extinguish PD≥ 1.5 × U₀≥ 1.7 × U₀ typical
PD magnitude at 1.5 × U₀Hold voltage, measure pC≤ 10 pC≤ 5 pC typical
PD after reeling fatigueRe-test post-cycle≤ 10 pC at 1.5 × U₀≤ 8 pC typical

4.3. Reeling Service Ampacity Derating

A cable wound on a drum cannot dissipate heat as readily as a cable run in free air or in a cable tray; heat generated in the inner layers of a wound drum must travel through multiple layers of cable before reaching the surface where it can be dissipated. VDE 0250-813 (and aligned IEC standards) account for this through ampacity derating factors applied based on the number of layers wound on the drum. The derating recognizes that the limiting condition for ampacity is the conductor temperature at the bottom (innermost) layer of the wound drum, which is the layer with the worst heat dissipation path.

Number of Layers on DrumDerating Factor (typical)Effective Ampacity vs Free-Air RatingApplication Note
1 layer0.8585% of free-air ratingSingle-layer drum or fully unreeled
2 layers0.6565% of free-air ratingLight-duty reel, partial wound state
3 layers0.4545% of free-air ratingStandard mining shovel reel
4 layers0.3535% of free-air ratingHeavy-duty dragline, intensive port crane
5+ layers≤ 0.30≤ 30% of free-air ratingProject-specific thermal analysis required
▣ Critical Specification Point — Ampacity in Reeling Service

The single most common ampacity specification error in reeling cable applications is calculating the cable cross-section based on free-air ampacity tables and ignoring the layer derating. A cable specified for 250 A free-air ampacity may deliver only 85–110 A continuous capacity when wound on a 4-layer drum without exceeding insulation temperature limits. Applications experiencing intermittent overload, repeated motor starting current, or partial unreeling during peak load operation can mask the derating problem until a heating event reveals it through accelerated insulation aging or, in severe cases, thermal failure of the innermost layer. The correct approach is to size the cable based on the worst-case wound configuration (typically the fully wound state at maximum continuous load), apply the appropriate VDE 0250-813 derating factor, and add a margin for transient thermal events. Feichun engineering supports this calculation as part of specification consultation; provide the reeling drum specification (number of layers, drum dimensions), continuous load profile, and ambient conditions, and the engineering team returns the recommended cross-section with full thermal analysis documentation.

§ 05
Type Test Battery and Routine Test Coverage

The VDE 0250 Part 813 Test Battery

VDE 0250-813 qualification requires successful completion of a defined battery of type tests, executed once per cable design and re-executed when significant design changes occur. Type tests demonstrate that the design is capable of meeting the standard’s requirements; routine tests, executed on every manufactured length, demonstrate that each specific length actually does. The following section presents the complete type test scope and routine test coverage.

Type Test Battery — Electrical VDE 0250-813 / IEC 60502 § Type Tests

Electrical type tests verify the design’s voltage withstand, partial discharge characteristics, insulation resistance stability, and dielectric properties under temperature extremes. The battery includes: AC withstand voltage at 4 × U₀ for 4 hours (long-duration withstand); impulse withstand voltage at standard impulse levels (1.2/50 µs waveform); partial discharge measurement at 1.5 × U₀ and 2 × U₀; insulation resistance measurement at 20°C and at maximum operating temperature (90°C conductor); capacitance measurement; and tan δ (dielectric loss) measurement at rated voltage. Each test is executed per IEC 60230, IEC 60270, or IEC 60502-2 procedures with full documentation of test conditions, measured values, and pass/fail determination.

Type Test Battery — Mechanical VDE 0250-813 § Mechanical Type Tests

Mechanical type tests verify the design’s mechanical performance under reeling fatigue, impact, abrasion, and tear loading representative of service. The battery includes: reeling fatigue test (the central qualification test, ≥ 50,000 cycles per the standard); cold bend test at -40°C around mandrel of specified diameter; impact test using calibrated impact hammer at specified energy; abrasion test per Taber method (CS-17 abrasive, 1 kg load) or alternative drum abrasion test; tear propagation test on sheath material (ISO 34-1); tensile load test on completed cable construction; and compression test simulating layer-on-layer drum loading. Mechanical tests are executed on representative production cable samples; results are documented in the type test report with photographs and measured values.

Type Test Battery — Material VDE 0282 § Material Tests

Material type tests verify the insulation, semiconductive screen, and sheath compounds meet specification both at manufacture and after accelerated aging. The battery includes: tensile and elongation tests on insulation and sheath samples (per DIN 53504); accelerated thermal aging at 135°C for 168 hours followed by tensile and elongation retention measurement; hot-set test at 200°C verifying peroxide cure crosslinking; oil immersion test (IRM 902 oil, 70°C, 168 hours) with mechanical property retention measurement; ozone resistance test on rubber components; and water absorption test. Each test verifies a specific compound property; collectively they confirm the materials are correctly formulated, correctly cured, and capable of long-term service performance.

Routine Tests — 100% Production Coverage Every Manufactured Length

Routine tests are executed on every manufactured length before shipment. The full routine test scope includes: conductor DC resistance measurement at 20°C (verifying conductor cross-section meets IEC 60228 requirement); AC voltage withstand at 4 × U₀ for 5 minutes (verifying insulation integrity); insulation resistance measurement at 500 V DC (target ≥ 10⁴ MΩ·km); partial discharge measurement at 1.5 × U₀ for medium-voltage cables; sheath spark test for sheath integrity verification; dimensional verification (overall diameter, conductor cross-section, insulation thickness, sheath thickness, conductor centering); and visual inspection. Each length ships with a Routine Test Certificate documenting actual measured values traceable to the specific length and to the underlying type test reports.

§ 06
Application Coverage and Procurement

Where VDE 0250-813 Cables Serve

VDE 0250 Part 813 reeling cables serve a wide range of applications across mining, port handling, steel, and process industries. The unifying characteristic of all these applications is the presence of a motorized cable drum that winds and unwinds cable as the equipment moves; the differentiating characteristics are voltage class, conductor cross-section, environmental conditions, and cycle count. Feichun TSCGEWTOEUS-EQ series cables are supplied across all of these application categories under VDE 0250-813 qualification.

6.1. Application Categories

Application CategoryTypical VoltageTypical Cross-SectionReeling Cycle Profile
Surface mining shovels (electric)3.6/6 kV95–185 mm²Standard class (≥ 50,000)
Walking draglines3.6/6 kV150–300 mm²Standard class
Rotary blasthole drills1.8/3 kV – 3.6/6 kV70–150 mm²Standard class
Stacker-reclaimers (bulk handling)1.8/3 kV95–185 mm²Standard class
Port container cranes (STS)6/10 kV120–240 mm²Enhanced class (≥ 100,000)
RTG / RMG cranes3.6/6 kV50–120 mm²Enhanced class
Steel mill ladle cars0.6/1 kV – 1.8/3 kV35–95 mm²Enhanced class + thermal
Tunnel boring machines (TBM)3.6/6 kV – 6/10 kV120–185 mm²Standard class
Underground mining (continuous miners)1.8/3 kV50–120 mm²Standard class + flame retardant

6.2. Specification Engagement Path

Procurement engineers engaging Feichun for VDE 0250-813 reeling cable specification typically work through a structured specification path that captures all parameters required for engineered supply. The engagement begins with the application context — the equipment type, cable drum specification (drum diameter, number of layers, drum drive arrangement), continuous and peak electrical load, voltage system, and ambient operating conditions. From this context, the engineering team develops the cable specification covering voltage class, conductor cross-section (with drum-derated ampacity calculation), insulation and sheath material selection (with environmental adjustments where required), reinforcement specification, earth conductor configuration, and reeling cycle qualification class.

Specification development typically completes in 5–10 business days for standard configurations. The engineering output includes the proposed cable specification sheet, the cross-reference to applicable VDE/IEC standards, the type test certificate references documenting the qualification basis, and the production lead time and pricing for the specified configuration. Where the application warrants third-party qualification — port crane projects, automated terminal projects, mining OEM equipment qualification — the engineering team supports the witnessed type test program through a recognized testing laboratory at the buyer’s preference.

▣ Documentation Available with Supply

Each VDE 0250-813 cable supply from Feichun includes documentation supporting the qualification chain from standard reference to specific delivered length. Documentation includes: the type test certificate documenting design qualification against VDE 0250-813 (and applicable IEC, DIN, HD references); the routine test certificate documenting test results on the specific delivered length; the certificate of conformance referencing the ISO 9001 quality management system and the specific applicable product standards; the conductor metal mill test certificate (where required by buyer specification); and the dimensional inspection report. Where the buyer’s specification requires additional documentation — flame propagation test results, smoke and acid gas release test results for restricted-ventilation applications, low-temperature qualification certificates — these are supplied as documented in the project specification.

§ 07
Conclusion

Standards-Aligned Reeling Cable Engineering

VDE 0250 Part 813 reeling cables are engineered products defined by a specific standards framework — not generic flexible cables marketed for reeling service. The standard establishes the construction architecture (Class 5 or Class 6 fine-wire conductors, peroxide-cured EPR insulation with semiconductive screens at medium voltage, concentric tinned copper earth conductor, textile reinforcement, peroxide-cured CPE or CR sheath), the electrical performance requirements (voltage withstand, partial discharge, insulation resistance, drum-derated ampacity), and the qualification testing battery centered on the reeling fatigue test that distinguishes a true reeling cable from a flexible cable that nominally fits the duty.

The Nexans (N)TSCGEWTOEUS family is one widely-recognized commercial implementation of VDE 0250-813 cable; the Feichun TSCGEWTOEUS-EQ series is a directly equivalent implementation of the same standard, engineered to deliver matched form, fit, and function across the conductor cross-section range and voltage classes covered by the original product. The equivalence is grounded in the shared standards framework (the cables are not “similar” to each other but are both qualified to VDE 0250-813), in matched construction at every layer, in matched type test scope and acceptance criteria, and in routine test coverage on every manufactured length. Operators specifying VDE 0250-813 reeling cable can engage Feichun on the same standards basis they engage any qualified VDE 0250-813 supplier.

Standard Reference
VDE
0250 Part 813 reeling cables
Voltage Range
0.6/1–6/10
kV phase-to-phase
Cross-Section Range
10–500
mm² Class 5/6 fine-wire
Annual Capacity
12,000
km mining and reeling cable
▣ Engineering Engagement

For VDE 0250-813 reeling cable specification, qualification documentation, sample cable supply for evaluation, or formal procurement engagement, contact the Feichun reeling cable engineering team. Initial engagement requires the application context (equipment type, drum specification, electrical load profile, ambient conditions) and the operator’s relevant specification or standard references (VDE 0250-813 by default, with operator-specific or OEM-specific specifications layered on as required). Specification consultation, cross-reference documentation, and technical proposal development are provided without charge for qualified procurement engagements. Production lead times for standard VDE 0250-813 specifications are typically 6–10 weeks from order confirmation; expedited delivery is available where production capacity allows.

Previous Article

Direct Replacement for Nexans (N)TSCGEWTOEUS: Heavy-Duty Mining Cable Specs

Next Article

(N)TSCGEWTOEUS vs. (N)TSCGEWÖU: Choosing the Right Reeling Cable for Open-Pit Mines

Write a Comment

Leave a Comment

您的邮箱地址不会被公开。 必填项已用 * 标注